Just a reminder, as we have
noted in previous updates, walkover construction can not begin in an area
until the sand delivery pipe has been removed. Pipe currently runs
from 2400 block of Bienville Blvd to just past Ponce de Leon.
Maps Below
Town walkovers
not yet begun are noted by a red line. Walkovers begun (either by Town or
Boardwalk homeowner) are in yellow & once finished walkovers are
marked with a green line. Materials were delivered to the Sehoy area for
the Town walkover there, but construction had not begun at the site as of
2pm May 4. |